Kinder Morgan – New Merchant Power Plant

Project Description

Aristeo teamed with Kvaerner Songer to construct a new peak power plant for Kinder Morgan Inc. Working an accelerated schedule over ten months, Aristeo constructed all building foundations, machine foundations, and cooling tower pits and basins for this 540-megawatt combined cycle power plant. We also excavated over 37,000 cubic yards of soil for all underground utilities.

Aristeo’s management and field supervisors coordinated and supervised throughout the project’s duration to place 18,700 cubic yards of concrete, install 1,100 tons of reinforcing steel, place and finish 129,000 SF of slab, and install nearly 4,000 anchor bolts.